STRATEGY
– MAINTENANCE, CAPITAL AND RISK
Dr. R A Platfoot
Covaris Pty Ltd
28 Joseph Street
Ashfield NSW 2131
Summary: This paper presents various methodologies and issues associated
with a total asset management process that embraces the use of capital
and maintenance expenditure to ensure assets meet the full spectrum of
operational requirements, including safety, performance and return on
investment. The broad range of issues associated with implementing asset
management mean that the work must be conducted within a cohesive framework,
even though different elements may have little in common with each other.
Pervading the entire process is a risk management process that is a function
of the condition of the asset base and the responsiveness to identified
needs.
1. INTRODUCTION
The Asset Management Plan (AMP) for an organisation embraces the following
broad areas:
• Business requirements of the asset base
• Capital management
• Risk management
• Long range maintenance strategy
• Short term maintenance control
• Budget management
The tangibles of the AMP are physical documents and systems that make
up the individual elements within the framework. In this case, they are
the outward signs of a business process, which is comprised of many business
rules. The business rules are defined in policy and then enforced through
the information system, work procedures and the responsibilities listed
in position descriptions.
The AMP has three objectives relevant to delivery of tangibles:
1. Creation and definition of a sequence of products and systems that
are to be used in accordance with the responsibilities of a position and
within the context of a team to ensure the defined business processes
are enacted efficiently and with minimum risk
2. Provide physical substance to a strategy that allows people involved
in the implementation of that strategy some simple goals and tools to
assist in its achievement
3. Enforce the business rules that make up the strategy, no matter how
intricate, interlinking or complex these rules are required to be since
the simple use of the tangibles will ensure that they will be followed
Stra tegy – Maintenance, Capital and Risk Page 1
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
A facility should be analysed wherever possible (pending data, time and
access for interview constraints) for the following:
1. Top cost areas (i.e. opportunities for savings subject to further detailed
analysis in these areas)
2. Work types and possible work efficiency
3. Reliability data in the form of defect trends
4. Responsiveness to backlog and rectification of defects
5. Risk management – as indicated by integrity considerations and
responsiveness of maintenance providers
6. Budget analysis
7. Anecdotal notes of relevance regarding asset management of the facility
In seeking to recommend on possible cost optimisation of the asset management
approach, an analysis should focus on determining specific high spend
areas that would warrant a detailed engineering investigation in the future,
and on aspects of the asset management highlighted by both data and interviews
that should be reviewed as to effectiveness in terms of methodology, systems
and resources.
Critical findings of past reviews have included:
• Provision of management practices that ensure a consistent approach
to all aspects of the AMP, supported by an accurate and useable information
system.
• Arbitrary reductions in budget, outside the context of the forward
maintenance plan of a facility, should not be allowed in the future by
an informed management team.
• Companies normally require greater discipline in the use of the
existing information systems, and to improve the use of feedback and analysis
in order to improve accuracy and content of the databases.
• The resource plans for major maintenance periods such as shutdowns
and plus the work critical paths need to be tested for assurance that
all scoped work will be completed within a scheduled overhaul. Changes
due to unforeseen condition should be challenged by the maintenance team
and over time reduced through improved tracking of condition.
• A means to improve the level of competitiveness in facility maintenance
work, including major shutdown work, needs to be investigated with options
to include the sub-contracting in of other major engineering organisations.
This paper considers aspects of a strategic asset management approach,
the exploration of maintenance improvement and concepts in effective measurement
of maintenance work performance.
2. STRATEGIC ASSET MANAGEMENT
The major steps in the Asset Management Plan include the following elements:
1. Business operational requirements for the assets to be maintained
• Long range business planning
Stra tegy – Maintenance, Capital and Risk Page 2
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
• Equipment capability requirements
• Long range asset management and development planning
2. Risk management processes to be established
• Safety, health and environment
• Operational performance losses and risks
• Area Risk Register
3. Integration of the Capital Plan with asset management
• Capital budgets
• Capital projects
• Improvement in equipment capability
4. Integration of engineering specifications (including statutory requirements)
• Statutory checks
• Engineering standards
• Design specifications
5. Development of long range maintenance planning and short term maintenance
controls
• Long range maintenance plan
• NDT and condition monitoring inspections
• PM history (condition of plant data)
• Short Term Maintenance Control
• Day to day operations and resource/access management
6. Planned maintenance
• MST schedule
• Major maintenance plan
• Shutdown planning
• Investigations
7. Ongoing review of maintenance effectiveness
• Scheduled corrective maintenance trending
• Unscheduled corrective maintenance trending
• Maintenance spending
8. Budget optimisation and continuous improvement
• Capital/operations
• Short term maintenance management
• Long term maintenance spending
9. Inventory management
• Inventory optimisation
• Spare parts ordering – warehouse and Purchase Requests
• Consumables (B2B processes)
Stra tegy – Maintenance, Capital and Risk Page 3
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
10. Use of support systems
• CMMS
• Zero-based budgeting
• Inventory management
• Maintenance optimisation tools
11. Technical procedures
• Procedure optimisation (eg RCM, PMO)
• Standard jobs
12. Reporting
• Financial
• Budget
• Maintenance backlog
• Work completion
• Work quality
• Diversion to schedule
13. Sustainable system considerations
• Documentation
• Auditing
• Position Requirements
• Training
3. CAPITAL MANAGEMENT
Capital management includes:
1. Annual Capital Budget
2. Capital Projects
3. Monthly CAPEX Forecast
The logic of this grouping follows standard capital management principles
as shown in the flow chart below: Set Capital Plansand BudgetConduct CapitalWork
as PlannedReport on ProjectVariances andCompletions
Within the AMP, the development of capital projects follows a three-stage
process:
• Identify the need to be met and the scope of works
• Develop a suitable design
Stra tegy – Maintenance, Capital and Risk Page 4
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
• Install that design within a project and commission the design
The element Capital Budget is concerned with the first stage of capital
project work, namely identifying the necessary projects to be undertaken,
their timing and allocated budget. These are driven by business imperatives
established by the Equipment Long Range Asset Management and Development
Plan (ELAP). Hence this element is concerned with matching planned outcomes
from the Capital Plan with requirements from the ELAP.
The ELAP contains the following items: list of issues which represent
long range limitations to the capability of the asset to perform safely
and with no threat to the environment, long range limitations in process
capability to be considered for improvement, and the list of corrective
actions, investigations and investment to address the issues and limitations
described above
Capital Projects is concerned with reporting back on the improvement in
asset capability and what operational performance levels can be expected
as a result of the capital work. Hence we are not so much concerned with
the day-to-day management of capital projects, which is the subject of
a company’s project management guidelines, but rather how the outcomes
of the capital works can be used operationally.
The Monthly CAPEX Forecast is associated with monitoring the capital expenditure
and assisting with identifying opportunities for savings.
4. LONG RANGE MAINTENANCE MANAGEMENT
The management of the long-range maintenance plan covers:
1. Life Cycle Plan
2. Equipment condition status
3. Expert services such as NDT and condition monitoring
4. Long Range Maintenance Plan
The logic of this grouping is shown below. There are a number of inputs
to the Long Range Maintenance Plan, and it is managed in an interactive
manner with other elements of the maintenance strategy, namely execution
of works and the Short Term Maintenance Control (refer Section 5). This
section has been confined to the key inputs regarding overall strategy
and plant condition. Relevant inputs such as Engineering requirements
(including statutory checks) and reliability analysis are treated elsewhere.
This also is indicated on the diagram below.
Stra tegy – Maintenance, Capital and Risk Page 5
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
EngineeringInputs(eg statutory,standards)Reliability andUnplanned WorkConcernsNDT
andConditionMonitoringDrivers for Long Range MaintenancePolicy onMaintenancePrioritiesLife
Cycle PlanRisksBusinessRequirements forAssetsMandatory WorkReliabilityImprovementEquipment
ConditionPrioritiesLong RangeMaintenance PlanEquipmentCondition StatusJobs
for MST Schedule, Investigations, Major Maintenance PlanRepeatable majortasksStandard
tasks repeatedon a regular basis
As can be seen from the diagram, the Long Range Maintenance Plan will
draw information from elements covered in other sections of this paper.
The logic with respect to the placement of the reliability elements in
Section 5, which is the Short Term Maintenance Control, is that reliability
reporting including corrective actions is a key element in the continuous
improvement loop of the short-term maintenance approach. The reliability
reporting is allocated to people more concerned with the short term than
the long-term perspective, even though the local area personnel will consider
the reliability data in formulating the Long Term Maintenance Plan.
The three key inputs into the Long Term Maintenance Plan are policy, repeatable
major tasks and plant information. Policy is concerned with priorities
and requirements of performance that have to be met. The plant information,
whether it is statutory demands, reliability or condition, identifies
needs areas for work to be done.
4.1 Criticality considerations
The elements in the LRMP need to be sorted according to criticality considerations,
such as those tabulated below:
Options
Priority
Consequences
Maintenance/ Capital Spend
S - Safety
M - Must do
1 - High
P - Production Capacity
L - Long Term (Item will probably be viable in the long term, but
2 - Medium
Q - Process Efficiency
M - Maintenance
Stra tegy – Maintenance, Capital and Risk Page 6
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
open for consideration)
O - Optional (Do not do if item is not viable in long term
3 - Low
C - Maintenance Cost
C - Capital
There is a strong correlation between the Options and Priority criteria.
The explanation of the Priority criteria is:
High
Must do within twelve months
Medium
Must do within three years
Low
Should be considered within the next three years
There is also a strong correlation with the Consequences options, which
may be considered to provide more of an explanation of the reason for
the task. For example, Safety tasks will in general carry a High priority.
Often capital issues considered under the Capital Plan are included within
the LRMP. This is because the timing of the tasks will coincide with periods
of major maintenance, and there is some advantage in determining lump
sum monetary requirements for a given year or month. The definitions for
maintenance and capital spend can beset according to the following:
Capital Expenditure
- Improvement expenditure
Maintenance
- Repair expenditure
Replacement of asset
Rebuild to original condition
Rebuild to a condition which improves subsequent maintenance
Replacement of a part with a modern equivalent
Rebuild to a condition which improves original capacity: this includes
capacity, efficiency, life span or economy of operation
Stra tegy – Maintenance, Capital and Risk Page 7
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
4.2 Exhibit of a LRMP
An extract from a working LRMP is tabulated below. It can be seen that
there are three kinds of work that need to be covered:
1. Ad hoc major tasks
2. Repetitive tasks, particularly inspections and overhauls
3. Tasks that can be anticipated at some time in the life cycle management
– typically replacement or complete refurbishments driven by results
from the inspection program
History
Kiln
Item
Equipment
Equipment Details
Equipment Number
Replacement Value $,000 per item
Last Replacement
Life (Yrs)
Last Replacement
Hydrate Feed System
1
A1
FeedBin
T661-11
1
A2
Apron Feeder
AF661-101
50
48K refurbishment 9/00
1
A3
Spillage Conveyor
C661-101
1
A4
Belt Weigher
BW661-102
1
A5
Screw Feeder Drive, Screw and Tube
Liner
SF661-103
40
Screw Tube
35
Changed in 2000
1
A6
Feed End Hydrate Lifters
Elevator Pot
ELV661-346
1
A7
Structural/platforms
Major maintenance
Routine maintenance
Stra tegy – Maintenance, Capital and Risk Page 8
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
Risk
Scope
Budget$,000
Problem
Consequence
Risk Type (E,S,B)
Likelihood
Rating
Proposed Work
Expenditure Type
Cost ($,000)
Priority
2002
2003
2004
2005
2006
Hydrate slowly
Hydrate lost to environment wears lining
E
4
2
Refurbish
M
x
2004
x
Screw feeder
Screw feedealignment isdifficult r breaks
B
4
4
Change out tube liners every 3 years
M
x
2004
x
Screw feeder
Screw feedealignment isdifficult r breaks
B
4
4
Change out screw tube every 10 years
M
x
2010
M
x
R
x
x
x
The exhibit demonstrates how clearly the ad hoc work stands out within
a tightly specified asset base, plus some of the information collated
to justify the long range expenditure.
The development of the costs for the repetitive major maintenance work
is accumulated from historical spend profiles. This spending is allocated
across each of the equipment areas contained within this scope of work.
Stra tegy – Maintenance, Capital and Risk Page 9
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
5. SHORT TERM MAINTENANCE CONTROL
This area of the AMP covers:
1. Unscheduled corrective work
2. Planned work list
3. Maintenance schedule
4. Maintenance backlog
5. Inventory review
The elements here are concerned with the day-to-day maintenance of the
asset base. The four main participants include:
Maintenance Supervisor – managing the planned (CMMS-generated) work
plus aspects of the corrective work, and revise inventory holdings
Operations/Shift Superintendent – managing the corrective work and
coordinating access to the plant
Planner/Scheduler – plan tasks and schedule work, coordinate plant-wide
services
Engineering – provide engineering authorisations of work scopes
as required
The intent here is to find means of assisting people in their tasks to
ensure optimum efficiency and to manage residual risk such as associated
with plant access priorities and backlog.
5.1 Backlog Management
Backlog criticality is determined by the following formula:
Risk = Asset Criticality x Task Criticality
In one application a critical task on a critical item carries the maximum
score of 25. The risk matrix is as follows:
Asset Criticality
Task Criticality
1
2
3
4
5
1
1
2
3
4
5
2
2
4
6
8
10
3
3
6
9
12
15
4
4
8
12
16
20
5
5
10
15
20
25
The policy for handling backlog should be:
Stra tegy – Maintenance, Capital and Risk Page 10
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
Level
RIME
Maximum time in Backlog
Remedial Action
3
1 – 8
Up to 2 years
Review if task is necessary – delete if not; increase task criticality
if it is
2
9 – 12
Up to 3 months
Increase task criticality to expedite attention
1
15 - 25
No more than 2 weeks
Urgent priority to address task
The snapshot of tasks in backlog for each cost area should be monitored
with the following plot considered:
Facility Cost Area 0 5 10 15 20 25 30 0 500 100150200Days in Backlog Risk
A monthly report on backlog should address the following:
1. Level 1 tasks in Backlog and time as to when that work will be completed
2. Level 2 tasks in Backlog and escalation of critical tasks to Level
1, and time when remainder will be addressed
3. Level 3 tasks discarded from Backlog
In the examples listed above, there is a considerable time spent in Backlog
for many work orders. Obviously there will be establishment problems to
tidy up the long term backlog work.
5.2 Work Type Analysis
Three dominant types of work are typically used:
1. Corrective Actions
2. Breakdown Maintenance
3. Preventative Maintenance (PM)
Corrective actions are predominantly driven by inspection work and operator
feedback. We are concerned with the following issues:
Stra tegy – Maintenance, Capital and Risk Page 11
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
• Time spent in various types of work – is maintenance proactive
or reactive?
• Proportion of Breakdown work and Corrective work to PM work for
different types of equipment.
In one example, the split of work for year 2000 was split as follows:
Corrective
Breakdown
PM
Area 1
N work order
881
211
950
N labour hours
26501.76
2446.28
10956.58
Area 2
N work order
361
51
579
N labour hours
7594.98
3076.25
32648.13
Area 1 is distinguished by no redundant plant so keyhole maintenance and
consequent high rates of corrective work are required. Area 2 consists
of large assets, any one of which can be off-line in a planned shutdown.
Redundant plant of this type has a consequent high work load in PM work,
with the challenge to assure cost effectiveness of the work.
The proportion of proactive work to total work is defined as the sum of
work types PM, major maintenance and inspection to the total body of work.
The resulting KPI for the above data is:
Area 1 31.9%
Area 2 75.7%
An appreciation of the distribution of work for various equipment types
in Area 1 is shown in the plots below. The type of work within a calendar
year are plotted for various equipment types, eg P6 (pumps) and so on.
Stra tegy – Maintenance, Capital and Risk Page 12
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
PM Work 0 500 1000 1500 2000 2500 F6 65 P6 CV HC L6 C6 T6 VP DB V6 CN
SU 66 AC K6 PU SL Equipment Man Hours
PM Work
Breakdown 0 200 400 600 800 1000 1200 1400 P6 C6 F6 T6 65 L6 HC SU CV
AC 66 CN DB K6 PU SL V6 VP Equipment Man Hours
Breakdown Work
Corrective 0 200 400 600 800 1000 1200 1400 T6 C6 P6 F6 65 V6 HC VP CV
SU CN L6 66 AC Equipment Man Hours
Corrective Work
The key issues that were identified in this analysis included:
1. C6 PM spending should be reviewed – is it sufficient for their
current duty?
2. T6 corrective work is high – appreciate that there are access
problems, but the total spending should be reviewed for effectiveness.
3. P6 breakdown spending is high – why isn’t the corresponding
PM spending addressing these problems?
6. CONCLUSION
The challenge for asset management is to provide a credible statement
on a strategy that will ensure the organisation can sustain their asset
base and its business mission in a long term cost effective manner. An
imperative for this issue is the need to reduce overall expenditure to
meet gaps between the sum of individual budget submissions from all areas
across a facility and the total organisation maintenance and logistics
budget guidance figures.
To achieve this the conduct of the asset management plan has to be guided
with feedback on the following issues:
• Distribution of costs across systems and areas
• Efficiency of the expenditure – reactive versus proactive
maintenance plus anecdotal notes on known problems
Stra tegy – Maintenance, Capital and Risk Page 13
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
• Effectiveness of the expenditure – management of the reliability
and capability of the systems, where capability represents ability of
an asset to provide its intended function with expected levels of flexibility,
efficiency and quality
Long-range maintenance strategy can reflect a plan that at a minimum forecasts
out to 5 years hence and includes the following:
• Plant condition assessment and life assessment
• Identification of major maintenance improvements, where major
maintenance normally refers to overhauls or shutdowns
• Investigations and management of long term risk
• Planning of major maintenance periods
• Review of the cyclic planned work lists, which may be called the
Maintenance Plan, although this Plan may also include major maintenance
improvements
• 5-year budgets
Normally the management of the long range maintenance is integrated with
management of the Capital Plan of an asset base, since periods of major
maintenance normally offer times of access for capital upgrades and configuration
changes. There are also links between capital and major maintenance as
capital change-out may address long-standing maintenance problems and
capital refurbishment or change should lead to modification of the Maintenance
Plan.
Short-term maintenance control is normally expected to have a twelve-month
focus and is concerned with:
• Scheduling of work from the Maintenance Plan, outstanding requests
for corrective maintenance and any non-urgent breakdown work into planned
maintenance periods
• Response to equipment inspections and condition monitoring that
identify items requiring immediate rectification
• Urgent attention of breakdowns that cause immediate loss of currently
required capability
• Management of urgent risk issues that need attention within the
next twelve months
• Certification, approval and logging of configuration changes
• Budget management and tracking of expenditures
• Development of budget for the following twelve month period
• Scheduling of the work packages and management of major maintenance
periods that fall within the twelve month period, including resource management,
expenditure and supply of materials and purchased services
• Developing detailed scopes and resource plans for major maintenance
periods that are imminent
Stra tegy – Maintenance, Capital and Risk Page 14
R A Platfoot
Covaris Pty Ltd FMMS Conference, 2001
External to this set of work, but included within the overall business
of asset management are:
• Interpretation of the broad overall business targets in terms
of operational requirements for specific assets and groups of assets
• Planning ahead to check likelihood of asset capability being able
to meet operational requirements
• Gap analysis between operational requirements and operational
performance
• Risk identification including hazards to capital, mission, safety,
health and environment
• Capital planning to improve the capacity, efficiency or cost impact
of using the assets to achieve operational targets
• Engineering support including establishing standards to be met
and design out of intractable problems or operational limitations
ACKNOWLEDGEMENT
The author acknowledges the assistance provided by many companies, his
colleagues at Covaris and many experts within the Australian maintenance
community to the research described in this paper.
Comments on this paper can be emailed to r.platfoot@covaris.com.au.