| RISK
MANAGEMENT VERSUS COST MANAGEMENT
Dr. R A Platfoot
Covaris Pty Ltd
28 Joseph Street
Ashfield NSW 2131
Summary: This paper describes the necessary trade-off between risk management
and cost management in a modern, performance-based maintenance contract.
Risk management is achieved by an effective, procedural-based PM system
implemented using a scheduling process and observing a previously developed
resource plan. Through competitive tendering, the resources available
to implement this plan are lean – the primary cost driver in such
contracts being the scheduled labour commitments. As a consequence a maintenance
strategy needs to be clearly established that sets out the task areas
for the work force, and then drives a detailed maintenance plan, which
in turn drops cards into the regular schedule. A case study describing
this process is included where the bulk of the work is made up of PM tasks
with little allowance required for corrective maintenance.
1. INTRODUCTION
A modern maintenance contract requires the delivery of expert work using
established business systems for either a tendered lump sum or a cost
plus process where profit may separated from recovery of incurred cost
and paid on a performance basis. In providing this service it is understood
that the client is relying upon the advice, skill and judgement of the
contractor in the planning and performance of the maintenance activities.
To facilitate the delivery of the maintenance strategies required in a
maintenance contract, the contractor will tailor a generic strategy for
a type of site. This strategy is then provided to a number of facilities
that are designated to be of this site type. The sites are differentiated
by service requirements, complexity of assets, level of manning and criticality.
Remote sites are specifically treated differently from sites close to
both operational manning and maintenance hubs, where hubs are defined
as contractors’ depots or local subcontractor facilities.
In the event that another category of facility needs to be added to this
list during the course of a contract, the list will be updated and the
maintenance approach suitably modified. Hence the maintenance strategy
may well evolve throughout the term of the contract, often in response
to client concerns. A successful contractor intends to leverage effort
and resources as far as possible from a labour pool wider than the specific
contract in order to deliver significant cost savings to the client. Using
this modular approach the contractor is able to reduce the workload in
maintenance optimisation and thereby ensure that optimisation of planned
work, expenditure and numbers of dedicated resources is delivered throughout
all facilities in the scope of works.
The intent is to identify specific areas for maintenance savings to the
client so that key areas are listed for immediate savings in expenditure
and the strategy by which these savings may be achieved is identified.
The strategy can change due to the following:
1. Reduction in the scheduled overhaul work – this can be beneficial
where maintenance budgets include a set amount based on an assumption
of hours under this item. Risk Management versus Cost Management, Dr R
Platfoot, Covaris Pty Ltd 1
IIR Maintenance Management 2002
Auckland New Zealand 2002
2. Elimination of forced work by investigations and consequent, less frequent
correction activity.
3. Work place efficiency, which will have the outcome of reduced real
costs of maintenance.
4. Reduced infrastructure costs such as water and energy expenditure.
5. Extension to the life of capital assets with consequent financial returns
associated with delay in commitments.
In this paper the trade-off between risk management and cost management
is specifically explored in terms of the maintenance strategy. The primary
costs driver is the resource base deployed to the contract, and competitive
tendering will mean that this base is lean. This has a flow-on impact
on what may be feasibly achieved in terms of risk management let alone
continuous improvement. Promises made at the time of tendering may not
be delivered due to resource limitations rather than lack of contractor
will.
2. MAINTENANCE STRATEGY
A maintenance contractor is expected to have the necessary knowledge and
understanding to implement maintenance improvement techniques. One approach
is provided below and covers the range of maintenance strategy concepts
referred to in this paper. It should be noted that this approach is not
undertaken in isolation from external factors such as OH&S obligations,
developments in the information systems and the introduction of technology
opportunities to upgrade condition monitoring. As the contract progresses,
other external factors will come into play, and the implementation strategy
is designed to be sufficiently robust to integrate with these.
It shows five key stages, moving across the page:
1. Plant dictionary – identification of assets to be maintained
2. Identification of equipment types
3. Development of Master Plans for the equipment types (eg RCM process)
4. Allocation of Master Plans to specific items of equipment
5. Development of time schedules for preventative maintenance
It should also be noted that these stages are implicit in the maintenance
plan provided elsewhere in this tender. The contractor is required to
provide PM schedules for the client’s assets in accordance with
this process. It is critical that the client can remain confident that
commitments on maintenance improvement will be fully met in the project
term.
A few key points should be noted:
• The process needs to be mapped to the system capability of the
works management system – information trapping for work, reliability,
costs, spares and so on is necessary to support improved planning and
work management
• The process is based on proven methodology – to achieve
detailed implementation in the field, the finer points of training, organisation
and business systems need to be addressed
• The process is contractor/out-sourcing tolerant – the location
of the maintenance resources is not an issue and this assists with the
improvement of sub-contractor quality
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
2
IIR Maintenance Management 2002
Auckland New Zealand 2002
Plant Dictionary- parent/childhierarchy- reasonable coverageCriticality
Review- formal method- driven by ProductionPlant Issues- running problemsNeeds
to bechecked forequipmentredudnancy andagainst processflow chartsCommissioning
ofNew PlantPosition Descriptions- who hasresponsibility forimprovement
itemsIdentify GenericEquipmentMaster Plans- process for eachtype of equipmentAllocation
ofMaster Plans toSpecificEquipmentTime Schedulingof PM'sLevel 3 condition
monitoringCurrently usedfor whatequipmentProcedureTechnologyOne off monitoringStandard
periodicchecksMaintenance systemstrainingPermit to work systemor equivalentRisk
controlsEnvironmentalmanagementExternal InfluencesPronto & DEMSsystems
trainingPronto Training- Standard jobs- Lubrication schedule- Maintenance
routes- PM schedules- Inspection data managementLevel 3 conditionmonitoring
coverageProcess critical itemsRisk Audit- Operational- Safety- FinancialRCMProcessFMECACondition
monitoringroutinesLubricationspecificationsOperator CapabilityAnalysisInspection
types- Operator checks- Trades check sheetsPlant IDsPlant IDsStandard
OperatingProcedures edit- inspectionsCondition monitoringScheduleLubrication
ScheduleStandard OperatingProcedures edit- reliability trackingPlant IDsPM
Plan- inspections- scheduled overhaul/discardMajor MaintenanceProgram-
Effectiveness checkInformation compiledProcedures compiledPronto updatedInspection
technology identifiedStandard Operating Procedures establishedCheck Sheets
updatedBudget ProcessesCondition-basedMaintenanceCOSTSBudgetinformationKPI'sShift
rostersWork allocationMonthly scheduleManage staff absenteeismImproved
technical training- instrumentation/electronics3 week work plan
Figure 2.1 Maintenance strategy overview
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
3
IIR Maintenance Management 2002
Auckland New Zealand 2002
• The process exploits the use of common types of equipment across
many work places, leveraging the contractor’s experience from these
sites
• The process incorporates external issues such as a Permit to Work
System which may be extended to job safety plans attached to procedures,
and which are in keeping with the most stringent OH&S requirements
The PM procedures are then attached to work orders issued by the works
management system and are responsible for ensuring quality of work completed
and a format for data to be collected such as performance measurements
and assets condition This process, plus its integration with the works
management system is shown on Figure 2.1
Cost savings are sought in the following areas:
1. Reduction of one-off, inefficient corrective maintenance work –
reducing shift requirements and moving staff to day work.
2. Reduction of scheduled overhaul/retirement work in major maintenance
periods.
3. Reallocation of staff from minor inspection and corrective work to
plant improvement work under separate budgets.
Operational savings are sought in the following areas:
1. Avoidance of infrequent, one-off large losses.
2. Avoidance of hidden failure modes, e.g. protection systems, control
devices.
3. Capture and solution of minor problems before they become major problems.
4. Improved plant capability through plant improvement work – throughput,
control, flexibility, safety, etc.
These factors are the fundamental building blocks of the long-term maintenance
strategy in reducing life cycle costs. Cultural improvement, which has
intangible benefits, are sought in the following areas:
1. Improved operator communication skills in description of problems encountered
during inspections.
2. Information system closing the loop from problem identification to
problem closure and feedback.
3. Integrated operator/maintenance problem solving.
Capital reduction may be possible through improved life cycle management,
but this is dependant on whether or not functional capability/technology
upgrade is the primary driver for expenditure in any case of a capital
upgrade. If there are deficiencies in lubrication, smooth running, scheduled
replacement of consumable parts and so on, this program will address these
issues without having to rely on capital change-outs of worn out equipment
or plant.
3. RESOURCE PLANNING
There are three primary sections to the preparation of the Maintenance
Plan and establishing the required resources to implement it:
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
4
IIR Maintenance Management 2002
Auckland New Zealand 2002
Contractor CorporateProceduresDetailed procedures fromother sitesCorporate
ProceduresMaster Job PlanWeeklyLevel 1- OperatingChecksLevel 2 - Trades
PMLevel 3 - Cond. Mon.Master Job Plan isallocated to maintainableitems
at specificlocationsPM ScheduleJanFebMarA345-789A345-646B245-876C129-456C129-457151015105101101010121012AprPM
ProcedureCombinesMaster Job PlanwithEquipment specificdetailsIssue a Work
OrderPM Work OrderCapture cost dataplus check sheet forplant conditionCondition-basedMaintenance
Work OrderIf plant condition warrants work tobe doneComputerisedMaintenanceManagementSystemMonitoring
by Senior Maintenance EngineerMaster Job Plans/ PM Schedule updated byScheduler
Figure 3.1 Maintenance procedure design
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
5
IIR Maintenance Management 2002
Auckland New Zealand 2002
Master Job Plans – the basic procedures employed by trades staff
to maintain items. Procedures to be sufficiently well designed that the
contractor understands the costs of work and can provide for it in the
lump sum portion of the contract. Further, the effectiveness and frequency
of each procedure to be sufficient to avoid unforeseen or corrective action,
as much as possible.
PM Schedule – a time-based spreadsheet allocating Master Job Plans
to specific items of equipment, identifying equipment specific information
plus the timing of when the procedures will be scheduled to occur.
PM Procedures – Works management system documents that integrate
procedures from Master Job Plans with equipment-specific information,
and subsequently can be provided as field data to the trade staff.
3.1 Master Job Plans
A contractor should be able to leverage a comprehensive data base of highly
refined job procedures, covering the broad range of assets and maintainable
items relevant to the client’s site. Each job procedure has a detailed
list of tasks, necessary observance of Standards and statutory obligations
plus OH&S and criticality information. This process and the use of
such Master Job Plans is shown below.
Corporate DataBase of JobProceduresMaster Job PlanMaster Job PlanMaster
Job PlanDifferentManufacturersDifferent VariantsPM ProcedurePM ProcedurePM
ProcedureDifferent AssetLocal AccessIssues for AssetsPM Work OrderScheduleWork
OrderWork Order.......Many WorkOrders over TimeOH&S, Statutory Risk,
Environment, StandardsAsset CriticalityWork OrderCriticalityWhat happens
if work isnot done?What happens if asset isnot available for service?What
is a reasonable dutyof care for the equipment?Issuing work to theMaintenanceteamVariations
due toAssetconfigurationVariations due toManufacturer ordesign
Figure 3.2 Generation of PM Procedures
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
6
IIR Maintenance Management 2002
Auckland New Zealand 2002
The figure above highlights the different levels of risk addressed by
each stage of generation of procedures, and ultimately down to the work
order level. The advantages of this hierarchical generation of PM procedures
area follows:
• There is efficiency in the generation of a comprehensive PM plan.
• RCM methodology may be applied at a very high functional level
to ensure optimisation of the task list of procedures – this is
typically the case of an RCM analysis of Master Job Plans where aspects
of design are taken into account.
• Changes in fundamental methodology due to new thinking, experience
or the introduction of new condition assessment technology may flow throughout
the company, the project and the asset base of a project in an efficient
manner.
• The contractor may assure its clients that it has learnt from
its extensive contract base and is passing on its learning to all clients
in an efficient manner. This represents a fresh approach by the company
to improving its service delivery.
4. CASE STUDY
To demonstrate the approach, the following tables are drawn from actual
spreadsheet schedules used in the planned rollout of a maintenance system
for widely distributed facilities. This type of maintenance contract may
be distinguished for example from maintenance for utilities or manufacturing
sites, but the principles translate well into these other applications.
The spreadsheet approach presented here can be used to not only implement
the start-up of PM schedules for new sites, but also to manage existing
sites’ risk profiles by the following:
• Identify potential savings in extending times between services
and modifications to scope of works.
• Identify deviations from actual schedules of service by comparison
of time sheets and completed PM schedules with the design specification
in the spreadsheets.
Supporting the spreadsheets needs to be an extensive database of PM work
procedures for a wide variety of plant, to which work associated with
each client site will contribute. The reader should scan along the rows
across the examples; so that first row of each example table follows on
to the first row of the following example table. The first set of tables
is drawn from the Master Job Plan sheet.
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
7
IIR Maintenance Management 2002
Auckland New Zealand 2002
AreaID
Functional Area
1
Air Conditioning
2
Cold Storage (food)
3
Cold Storage (non-food)
4
Cold Water Retic.
5
Compressed Air
6
Cooling Tower
7
Dishwashers
Functional Area groupings
Job Plan ID
Contractor Procedure No.
Equipment Name
Functional Group
1001
Air Handling Unit
Air Conditioning
1002
Air Handling Unit
Air Conditioning
1003
Chilled Water Valve
Air Conditioning
1004
Compressor
Air Conditioning
Columns 1-4 Master Job Plan Sheet
Manufacturer
Use
Criticality
Performance Requirements
OH&S Requirements
Muller
Climate Control
3
The temperature within the air conditioned environment is required to
be 22 degrees +/- 3 degrees C.
Confined space; Guarding of Belts; Electrical Isolation of Motor
Hiflow - Lamina
Climate Control
3
The temperature within the air conditioned environment is required to
be 22 degrees +/- 3 degrees C.
Confined space; Guarding of Belts; Electrical Isolation of Motor
Landis & Gyr
Climate Control
3
The temperature within the air conditioned environment is required to
be 22 degrees +/- 3 degrees C.
Carlyle
Climate Control
3
The temperature within the air conditioned environment is required to
be 22 degrees +/- 3 degrees C.
Guarding; Electrical Isolation
Columns 5-9 Master Job Sheet
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
8
IIR Maintenance Management 2002
Auckland New Zealand 2002
Consumeable Parts
Access
Associated equipment, Filters make: International filter company, model:
Pyracube.
Schedule maintenance to be carried out during the facilities normal hours
of operation.
Schedule maintenance to be carried out during the facilities normal hours
of operation.
Schedule maintenance to be carried out during the facilities normal hours
of operation.
R12 Refrigerant
Schedule maintenance to be carried out during the facilities normal hours
of operation.
Columns 10-11 Master Job Sheet
Time Required
Periodicity
Weekly
Level 1
Level 2
Level 3
Level 1
Level 2
Level 3
(Operational)
(Condition Report)
(PM)
(Performance)
(Condition Report)
(PM)
(Performance)
0
1
4
1
3
12
12
0
1
4
1
3
12
12
0
1
2
1
1
3
12
0
1
2
1
1
3
12
Columns 12-18 Master Job Sheet – Time and Periodicity Allocations
In this work we distinguish between four types or levels of tasks:
Weekly – periodic task that is brief and must be completed every
week; typically used for fire equipment checks.
Level 1 – visual and simple inspection; typically conducted on a
monthly basis by trades. Some local improvement may lead to Defence personnel
conducting these checks.
Level 2 – trades PM; typically conducted on a 6 monthly or annual
basis.
Level 3 – comprehensive inspection or condition monitoring check;
typically conducted on a 12 month basis.
Level 1 and Level 2 tasks may coincide, in which case the Level 1 task
is rolled up into the Level 2 task. The Level 3 task is conducted independently
of the other two types of tasks. Procedures are provided for all types
of tasks as required.
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
9
IIR Maintenance Management 2002
Auckland New Zealand 2002
The data on the Master Job Plan sheet is then automatically picked up
in the PM schedule work sheets for a specific site or facility. An extract
is shown below.
Equipment ID
Building ID
Condition
Criticality
Item of Equipment
Number of Items
SWHH0054
0382/OH021
3
3
HWS 275 Ltr
1
SWHH0055
0382/OH021
3
3
Circulating Pump H/W
1
SWHH0056
0382/OH021
3
3
Circulating Pump H/W
1
SWHH0057
0382/OH021
3
4
Air Break Tank Registered Non Portable 2000Ltr
1
Columns 1-6 PM Schedule
Functional Area
Master Plan
Manufacturer
Model No.
Serial No.
Location
Site ID
Hot water retic
14006
Rheem
620275N0
572867
PLANT ROOM 1
0382/OH
Hot water retic
17001
Grundfos
UPS-20-60B150
9526DK
PLANT ROOM 1
0382/OH
Hot water retic
17001
Grundfos
UPS-20-60B150
9506DK
PLANT ROOM 1
0382/OH
Retic Serve
31001
PLANT ROOM 1
0382/OH
Columns 7-13 PM Schedule
Hours Required
Months Periodicity
Weekly
Level 1
Level 2
Level 3
Level 1
Level 2
Level 3
Start Month
Level 3 Start
0
0.5
1
0
3
12
0
1
1
0
0.5
1
0
3
12
0
1
1
0
0.5
1
0
3
12
0
1
1
0
0.5
0.5
0
3
12
0
1
1
Columns 14-22 PM Schedule – Time and periodicity allocations based
on Master Job Plans
What the tables above demonstrate is the information requirements in a
PM plan. Based on the periodicity and duration of tasks established in
the Master Job Plans specifications, plus the start month specified for
commencing the PM cycle, it is possible to determine the expected trades
hour spent for each item of equipment per month. In the case of facilities
maintenance, this is a reasonable estimate of likely man hour requirements,
since the duty of the assets is not severe. In more extreme environments
such as utilities
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
10
IIR Maintenance Management 2002
Auckland New Zealand 2002
or manufacturing multipliers on the PM tasking is required to better anticipate
requirements for breakdown and corrective maintenance support.
An extract of the resource plan established in this study is shown below.
All Levels
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
1
2
3
4
5
6
7
8
9
10
11
12
1.5
0
0.5
0
0
0.5
0
0
0.5
0
0
0.5
1.5
0
0.5
0
0
0.5
0
0
0.5
0
0
0.5
1.5
0
0.5
0
0
0.5
0
0
0.5
0
0
0.5
1
0
0.5
0
0
0.5
0
0
0.5
0
0
0.5
Columns 23-35 PM Schedule – Hours per month for all types of work
The hours in the resource plan are sums of time allocated to the various
levels of work described earlier in this paper.
The raw numbers in the spreadsheet examples shown above are man-hours.
These may be converted into number of trades people required to service
the schedule per month through use of the equation:
tyAvailabilimonth x per days work of No.x hours/day 8monthper work of
hoursman Total people tradesof No.=
In this equation it is recognised that some months have less workdays
due to public holidays. Moreover, some months have a higher rate of absenteeism
due to leave. A further refinement planned for the immediate future is
to move from 8 hours per day to a calculated factor that takes into account
non-productive time, travel time and other time away from maintenance
tasks.
Final results for one notional schedule are shown below. The final results
show total numbers of man-hours and total number of trades people required
on a monthly basis.
PM Man Hours
Jan
Feb
Mar
Apr
May
Weekly
0
0
0
0
0
Level 1
29.7
20.45
27.95
20.45
20.45
Level 2
52.85
0.5
21.75
0.5
0.5
Level 3
12
0
0
0
0
All Levels
94.55
20.95
49.7
20.95
20.95
No. of trades staff
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
11
IIR Maintenance Management 2002
Auckland New Zealand 2002
Weekly
0.0
0.0
0.0
0.0
0.0
Level 1
0.2
0.1
0.2
0.2
0.1
Level 2
0.4
0.0
0.1
0.0
0.0
Level 3
0.1
0.0
0.0
0.0
0.0
All Levels
0.7
0.1
0.3
0.2
0.1
Extract from summary report of a PM schedule
4.1 Cost Analysis
The pricing of the tender is then based on an expected number of resource
hours, allowing for the following factors.
1. Direct overheads - leave
2. Statutory overheads – workers compensation, payroll tax
3. Award overheads – superannuation, redundancy
The base rate is established according to the craft type and the numbers
of hours per craft may also be extracted from a comprehensive resource
plan.
5. SUPPORTING AND REFINING THE MAINTENANCE PLAN
The contractor is expected to continue their proactive approach by analysing
existing data to identify equipment that would benefit from a inspection-based/condition-monitoring
program. Perhaps elements of these recommendations will not be taken up
straight away, but they will be fed into the maintenance plan review scheduled
to occur simultaneously with the identification and addition of new maintainable
items to the overall equipment list.
The figure also demonstrates the mobilisation strategy where the continuous
improvement process kicks off with risk appraisals and audits of the items,
leading to an initial check of the Master Job Plans and PM schedules established
within the first period of the contract takeover. This work, driven by
the Maintenance Engineer (who may be the Site Manager or some other leading
manager) and the Scheduler, will lead to revised equipment plans passed
to the client in accordance with the stipulations of the contract.
However this process will not end in the first cycle at the establishment
of the contract. It is intended to be a continuous improvement process,
with a cycle time of 12 months, leading to an annual review of maintenance
performance and financial performance.
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
12
IIR Maintenance Management 2002
Auckland New Zealand 2002
Audit of equipment tobring worksmanagement systemequipment list tocurrencyFault
callminimisationOperationalperformanceDesignimprovementsRisk AppraisalsConditionMonitoringSchedule
ReviewsProceduresRefinementMaintenance EngineerSchedulerSupervisorscross
check ofnew equipmentRevised equipment plans - maintenanceschedules, new
equipment, improvedinspections, revised procedures, currentcondition,
improvement plansSubmission of revised PM planContinuousImprovementReview
ofmaintenancestrategy- Master JobPlans- PM ScheduleMaintenanceReportingPriorities
forimprovementMaintenancePerformanceReviewOutcomesMaintenanceBudgetFinancialPerformanceProject
starts here
Figure 5.1 Continuous improvement – note the accountabilities
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
13
IIR Maintenance Management 2002
Auckland New Zealand 2002
6. CONCLUSION
The PM schedules presented in this paper provide a practical example of
the systems and approach a competent contractor employs when developing
a PM schedule and associated procedures for a preventative maintenance
system. The approach allows for continuous improvement, using the methods
described in the paper under a short term and long term maintenance strategy.
A short term strategy describes how the contractor will deliver the maintenance
plan, and the long term strategy describes how continuous improvement
in terms of both risk mitigation and cost down can be achieved.
In order for plant and equipment to continue to operate and maintain the
required performance criteria, appropriate statutory, predictive, preventative,
reactive and condition monitoring maintenance activities are essential.
These tasks can be established within a strategy for specific types of
equipment and then procedures applied to instances of these types across
the scope of works. This approach can offer substantial efficiencies in
maintenance systems design with a proportion of 1 Master Job Plan to up
to 100 PM tasks.
Current maintenance strategies, actually independent of whether they be
contractor or internal service provider, include:
1. The means to analyse work and expenditure that will identify opportunities
for feasible savings and performance enhancement
2. The ability to model projected maintenance costs on the basis of historical
performance and the risk profile of the site. This will allow the future
costs of providing maintenance to be reduced through applying the most
appropriate type of maintenance strategy
3. The ability to improve the planning of maintenance based on knowledge
of the condition of assets and measuring the outcomes of the work
4. An improved format for maintenance reporting and monitoring of outcomes
5. Development of the skills of the maintenance and operation team to
improve their capability in forecasting future problems, decision-making
and corrective action
These elements are contained within a business system as described in
Section 2 of this paper and are necessary to create and then maintain
the detailed types of schedules described in Sections 3 and 4.
ACKNOWLEDGEMENT
The author acknowledges the assistance provided by many companies, his
colleagues at Covaris and many experts within the New Zealand and Australian
maintenance community to the research described in this paper.
Comments on this paper can be emailed to r.platfoot@covaris.com.au.
Risk Management versus Cost Management, Dr R Platfoot, Covaris Pty Ltd
14
|