Managing the process of outsourced contracts and
agreements


Dr. R.A. Platfoot
Covaris Pty Ltd
Level 2, 107 Mount St
North Sydney NSW 2060
1. Introduction

 


Maintenance is a lifetime of sustained effort to ensure that the assets of a
company continue to provide a service that will ensure that the organisation
can provide its designated service. As a consequence a maintenance
contract has very different business goals from the provision of services
through construction or a one-off engineering exercise. The key goals for
such a contract include:
1. There is no end point to the achievement that can be marked as the
completion of the service. The effort must be sustained over the life of the
company.
2. The time frame for the services is beyond the life of the contract: while a
contractor may be retired at a designated period, the facility owner/user
will continue and so must the maintenance of its assets. Hence the
engineering decisions taken as part of the contractual services consider
much longer time horizons.
3. The effort must be sustained in the sense that the integrity of the facility is
only as good as its weakest part. If the outcome of the service is reliability
of the assets, then the quality of work must be uniform and sustained to
avoid a few weak areas which will undo the good work completed
elsewhere.
4. The outcomes of the services should be measured in terms of the
productivity of the client’s assets. Unlike most other contractor-client
relationships, maintenance success is intimately concerned with the
business success of the client who uses the assets to achieve the latter.
While these points are self evident, best practice maintenance needs to
progress even further in the value of its delivery. Since the services extend
over time, there are a number of issues that will lead current effective
practices to diminish in value. These include time-based damage
mechanisms that deteriorate the equipment and/or facility. Examples include
fatigue, wear and corrosion. As a consequence of this, reliance on reactive
maintenance with excessive corrective maintenance response will result in
deterioration of the assets. Secondly the people who manage and undertake
both sides of the relationship, including building supervisors, maintainers,
administrators and so, will change in and out of their positions. This leads to
forgetfulness where the lessons of the past o not guide the decisions of the
future, to incorrect choices being made and to the introduction of damage
through lack of skill in operation or repair. A third issue is the transient nature
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 2 of 16
of business, where the assets may be utilised for services beyond their
original design capability, or over a service life greater than their design life.
For all of these reasons, the business of maintenance must also
accommodate the following:
1. Sustained introduction of refined or original techniques to improve the
surveillance of the equipment or facility to detect life threatening damage
mechanisms.
2. Continuously improve the skill in both technical undertakings and
organisation/decision making of the maintenance staff. This will reduce
the risk of failure introduced by maintenance activity and ensure that
resources may be minimised but remain effective.
3. Continuously improve the clarity of communication between client and
maintenance staff to ensure that decision making for both task groups is
optimised.
This paper covers a number of the key issues that can lead to conflict during
the conduct of a contract, and also identifies some means by which
contractors and clients have learned to communicate and work with each
other. Key issues of scoping the works, mitigating against unwanted business
outcomes for both parties, considering capability of the service provider and
opportunities for value add are increasingly important in the day to day
association within an effective contract.
The spirit with which a good contract may be approached is less of
specification of works required, and more request for contributions from the
service provider. However to reach such a stage requires the development of
mutual trust and maturity on the part of both participants in the contract.
2. Reviewing the Asset Base
For commercial office buildings the contractor needs information for long term
planning including identification of the most critical items and trend of
conditions. He/she then needs checking strategies for taking on the risk of
maintaining designs made by other people, who typically have no focus on
the full service life. In design checking questions centre on alternative prices,
efficiency and controls which differ from the questions relevant to
maintenance. Evaluation of design weaknesses allows the contractor to plan
ahead for failures rather than just reacting to them.
Key aspects of a building review process are listed below:
• Review capability of Building Management System (BMS) –
functionality, data handling, reporting, interface to other systems,
efficiency monitoring possibilities.
• Thermomechanical efficiency audit of plant services – plant room,
cooling towers, chiller plant room, boiler plant room.
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 3 of 16
• Review of building operating requirements and matching with
availability of services.
• Air conditioning including management of sunny rooms, humidity
control and heating requirements (noting ACT weather is cold during
winter – what are the efficiency aspects of the seasonal adjustments?),
and changing room usage, say to computer rooms.
• Electricity metering – match consumption against budgeted baseline
established from past consumption. Reports to include $/month,
exceptions to the monthly bill, kW and MJ. Exceptions may take the
form of chillers operating incorrectly, incorrect tuning of HVAC, etc.
• Gas metering – same as electricity metering.
• Review of sensor position for BMS – eg air sensors located on ceilings
– list for adjustment for people comfort, energy efficiency and so on.
• Water consumption in cooling towers – flooding issues, overflow,
matching valves to pumps, adjusting levels, adjust timing of valves.
• Effectiveness of external contracts, eg fire systems, lift systems –
performance audits of third party contractors.
These issues are encountered on a daily basis by technical staff from the
service providers, particularly with a focus on energy conservation for their
client, possibly due to an energy performance guarantee in their contract.
In developing a strategy for the identification of equipment within facilities,
some thought has to be given to the inherent similarities across multiple sites
with a common purpose. Within the generic structure a hierarchy is evident:
• Functional areas are nominated which have a specific process.
• Within the functional areas distinction is made between those assets
that perform the function and those that monitor it.
• Monitoring is typically rolled up into PLC’s, SCADA and control circuits.
There is an issue as to where sensors, interlocks and other local
equipment should be allocated.
• Working assets (those that provide the function) are broken further into
mechanical or electrical components with electrical control under the
component, and mechanical components otherwise at the same level.
Usually associated with the generic structure is a general purpose area that
includes services and other systems providing functional support to the
process areas.
Policy on asset management covers three stages: asset creation, asset
update and asset retirement. The elements of the policy are briefly examined
under each of these headings:
Asset creation
Where is it in the plant?
Logic of the site in the existing number system.
Code for type of equipment.
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 4 of 16
Unique number to be allocated in the CMMS.
Where are the drawings kept?
Asset update
How can the contractors assist this process? Do they have full
responsibility for the process?
The client team owns the assets – is the terminology, numbering, plant
association and so on, relevant for their needs?
How are outdated drawings and documents managed?
How are single items updated?
Asset retirement
Decommissioning procedure – CMMS document to be completed
Asset not deleted from database – it is moved to a decommissioning
location whereby past history can still be accessed.
3. Linking Risk Mitigation Strategies with Maintenance Targets
Risk management is central to effective maintenance improvement, ensuring
that the analysis is conducted according to business priorities and that the
process is not sunk by the need to handle large volumes of data. A five level
risk ranking was established at one client site by the contractor:
1. No problems
2. Cosmetic problems, e.g. needs painting.
3. Requires work but is not process critical, e.g. hoses cracked.
4. Requires maintenance as soon as convenient, e.g. major oil leak.
5. Imminent breakdown, e.g. no oil left in the bearing.
The risk system needs to be utilised by a wide cross section of people. The
activities for maintenance and production are tabulated:
Risk Level Service Provider Client
1 Do not schedule work OK for use
2 Do not schedule work OK for use
3 Schedule work into a normal
program by bundling together
work in that area
CYCLIC MAINTENANCE
OK for use
4 Schedule work as soon as
possible
OPPORTUNISTIC
MAINTENANCE
Provide access
Not preferred to operate
5 Dispatch people now.
BREAKDOWN
MAINTENANCE
Ensure access to allow BD
task
Operate only in emergency
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 5 of 16
It is necessary that these rankings are agreed upon between the two parties
such that the risk level numbers carry the same meaning to both
organisation’s staff. The above classifications also need to be checked that
they correlate well with original corporate definitions such as used with OH&S
incident reports, environmental reports and so forth.
Risk is a score which may be employed in the following circumstances:
1. Setting priority for a work order
2. Acting as a qualitative measure from a visual inspection
3. Condition of the plant either as found at the start of a job, or as left
when the trades person completes a job
For example, an operator or maintenance person may identify a piece of
equipment as in condition 4, resulting from an inspection of the plant. Hence
a work order is raised with a risk level of 4. That carries meaning to both the
facility user and maintenance as per the table set out above. When the
trades person acquits the work, they should sign off that the condition of the
plant has been reset to a level 1 or 2.
The status of a plant needs to be reported so that facility operators are
continually aware of any threats to use. Levels of reporting which have been
suggested included:
Risk Level Client Management
Users
1
2
3 All level 3 jobs tabulated and
the summary considered
4 All level 4 jobs separately
tabulated with some being
scrutinised
All level 4 jobs identified
5 All level 5 jobs described All level 5 jobs identified
What this table means is that a log has to be kept with the operators,
identifying when an item of plant is subject to a risk condition 4 or 5. When
an item is repaired and returned to a level 1,2,3 state the fact must be
reported to the operators so that they know that the asset is free for use with
no restrictions. A trades person returning an asset from a level 4 or 5
condition should be obliged to complete a visual inspection and report to
ensure against secondary damage or other undetected damage.
Client management will need to be aware of the following:
1. The balance of work which is at risk levels 3, 4 and 5. High levels
of risk level 4 or 5 is a KPI that maintenance needs to improve its
effectiveness. In addition, such high levels would correlate to high
expenditure per job which is something we are trying to avoid.
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 6 of 16
2. Access to a summary of level 4 jobs on request. This is because
they may need a please explain as to why the job crept over the
level 3 mark and secondly, they may be aware of production
circumstances which may raise a level 4 to a level 5.
3. Detailed review of level 5 since these are direct threats to their
business performance. Each level 5 needs to be reviewed in detail
with the service provider to ascertain how it can be prevented in the
future. The number of level 5 tasks is as significant a KPI as the
downtime rate.
4. The number of level 5 jobs called in by facility users. The client
needs to ensure that their staff do not needlessly call in a level 5
job request which would incur the financial penalty of a call out.
4. Incorporating the Budget Process to Risk Management Targets
There is a need for a contractor to guarantee value for money not just
minimum cost. The cheapest service may not be the best and hence quality
has to be balance with expenditure. Sometime it may be worth the wait for
better value goods. Every contractor needs lift their service in order to
differentiate themselves from their competitors.
Reliability of service is important in the areas of skills and availability: that the
maintenance provider can address the clients’ problems in a competent and
timely manner. A typical contractor wants to be professional. Therefore they
need to keep track of what they did, how they did it, and did they help the
client with their budget? A maintenance contractor is a service organisation,
processing jobs, confident that they have the control to do the job, and that
they can reasonably forecast the future. That means keeping history on the
costs, how they invoiced it, reviewing the work, and if there was a fault, what
caused it and how could it be prevented it in the future?
If a contractor does not commit to a cost reduction drive he/she will not keep
the client. The author was asked once, “Should we increase value rather
than reduce cost”. The answer:” No, we always focus on reducing costs if we
wish to keep clients.” How do we define value except in monetary terms, e.g.
a OH&S risk can be priced and placed in monetary terms?
As the contractor works with the plant his/her learning about its technical
characteristics will allow improvements in the forward costing. This is based
on better appreciating its design limitations. If this can be recognised up front
then the learning curve can be steeper.
A contractor also needs to factor into a job the capability to manage
information. If they are too lean in this area then they cannot improve the
quality of their reporting or planning, which will have serious consequences for
client relations and effectiveness in keeping the contract. This will be
appreciated by an informed client, who will want improvements in informed
management.
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 7 of 16
To establish a useful financial analysis maintenance expenditure records for
the past three to four years usually need to be analysed. This avoids any
perturbation due to a major equipment problem skewing the trend shown up
by the analysis. It is also important to distinguish between expenditure during
operation when reliability is the principal focus and during refurbishment when
meeting project targets dominates.
The type of financial statistics which an analyst should be seeking include:
1. The percentage of expenditure on maintenance work that is due to
individual jobs in excess of a specific cut-off limit in value in
combined labour and materials. The cut-off limit varies with
application, but may be as much as $10,000. This can range from
40 to 70% depending on the industry.
2. The percentage number of hours these jobs take up. In one study
such jobs took up 60% of the booked hours but only represented 9%
of the total number logged in the system.
The source of savings may be ranked in accordance with the Pareto
distribution of the expenses, differentiated for whether or not they arise during
production. The point to the above two questions is whether or not there is an
opportunity to seek efficiencies in a small number of jobs (surprisingly small in
the example quoted) which will provide the maximum effectiveness in a
maintenance improvement program.
Another example of a financial analysis concluded in the following distribution:
% Total Budget
Overhaul Materials 45
Overhaul Ordinary Hours 26
Overhaul Premium Hours 3
Service Materials 13
Service Ordinary Hours 10
Service Premium Hours 3
Table 4.1 Hierarchy for expenditure
It is reasonable to assume that mechanisms were already in place for
minimising overtime, and that the current average levels were in keeping with
the then current level of manning. The means by which maintenance savings
can be achieved within each of the top four categories will differ as indicated
below:
Overhaul - Materials Improved protection of
assets.
Capital investment in
new assets.
Replacement of PM
tasks with predictive
Identification of key
causes of materials
degradation.
Fundamental study of
damage mechanisms
rather than trial and
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 8 of 16
techniques. error approaches.
Capital submissions
and tracking reliability
of new capital
investments.
Overhaul - Labour Optimisation of work. Improved analysis of
downtime causes.
Condition monitoring
during operation.
Extensive data base on
plant condition.
Planning strategies
based on forecast
problems and trends in
plant history.
Operation - Materials Equipment condition
assessment prior to
commencement of
production.
Extensive and rigorous
NDT checks.
Recommendations for
change-out during
subsequent overhauls
based on Pareto
analysis of materials
consumed during
operation.
Operation - Labour Avoidance of repetitive
work.
Improved
commissioning
strategies for
equipment.
Root cause analysis of
failure.
Condition monitoring
during operation.
Table 4.2 Opportunities for improvement
Maintenance improvement consists of the following aspects:
1. Savings do not mean that a specific job is deferred but rather it is
undertaken in such a way that it can be completed quicker (reducing labour
hours), with less material where possible, at lower unit costs of material
where possible and with an optimised scope of work which ensures that
costs are minimised.
2. A job may be deferred if it can be shown that other work would be
otherwise deferred and that this other work has a higher criticality. As part
of this, the assessment of criticality and hence the selection between work
must range outside a specific department and, for large jobs, outside a
specific facility.
3. The attempt for about a 12% saving in expenditure on a specific large job
will come about largely through improved planning practices associated
with improved labour practices. If these cannot be achieved then the 12%
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 9 of 16
target will not be met, and in that instance at least, the job may well be
considered to be optimised.
4. Maintenance improvement has to be demonstrable: say, X% of the past
year’s budget represents $Y, which is a targeted saving for next year
Hence through improved maintenance practices, field engineering will have
to demonstrate an increased completion of jobs, which would match the
injection of this sum, employing pre-improvement planning and work
practices.
5. Developing the Procedural and Skill Base
A major area for improvement is how the client communicates a problem
during a call out situation. Issues include describing the correct plant that
needs to be attended. The operator taking the call out needs to take down
specific information, which will be replicated on the work order. This can
include an event number by which the job will be tracked.
Part of the communication process for the contractor involves discussion with
the client where their operation may be too harsh for the plant. Examples can
include the frequency with which filters need to be replaced. Maintenance
contractors care for the equipment on the client’s behalf - they usually do not
have any other input apart from determining whether or not they are getting
the performance they want from the equipment.
Staff related damage to the assets can initiate training by the contractors to
limit this problem. As a consequence, there is benefit in having a consistent
means for tracking downtime and providing a consistent report back to the
client. For this to happen the contractor needs to make it simple for staff to
record and access the information.
In one case after hour calls were not accurately describing the nature of the
job, leading to a blow out in premium time work. Check sheets were
introduced to the client to ensure that correct information is relayed to the call
out. Event numbers are assigned to each call that assisted in trending the
outcomes of each call.
One of the contractor’s major problems is that the staff have insufficient
information as to how the equipment is supposed to operate. This
understanding could provide early warning of problems, particularly those
associated with the sequencing of equipment. To determine what equipment
is critical, the following information is required:
• Is the failure predictable?
• What is the necessary response time?
• Does the client see value in the work?
• Do a set of standards exist?
• What is the cost of maintenance versus work deferred?
• Is the service life of components known?
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 10 of 16
It is often a cultural issue to improve people to appreciate the need for this
information, rather than a systems improvement or technical issue to achieve
improvement. As one contractor wrote to the author:
Our strengths in the business are our people, the number of people and our
knowledge. Our weaknesses are no procedures which can then be
customised to suit a particular client. We need quality requirements which are
documented.
Trades people need to see some reports on condition, which may be
achieved through tool box meetings where shortfalls in service are identified.
Often no hard information is provided to them, but the supervisors/managers
talk to them. This is may be due to there being no history from which to
report since the job for that particular contractor is so new. Alternatively the
reporting focus is skewed to performance indicators to achieve the financial
targets.
There is a need for training with people in the work force for 30 years plus
newcomers all needing new insight and techniques. It is common experience
that when reporting to trade staff, it is better to talk than to provide paper.
While the typical sort of people the contracting companies like to employ are
good problem solver, there is a need for information literate trades staff able
to exercise strategy in actions at the equipment base.
Indicators that skills are lacking include feedback from the clients through
project managers on possible lack of knowledge or work skills. Consideration
is then given to either training or the employment of subcontractors. The
deeper structural problems for contractors are that their otherwise talented
trades staff are not appreciating the meaning of work type trends, reliability
charts or trends in inspection reports.
6. Managing the Ongoing Relationship between Client and
Contractor
It is important for the contractor to team with the clients. The relationship
builds on mutual trust. There needs to be a general ability to get on with each
other. Hence the association needs an open book approach that sets out:
• What is the contractor going to do
• When will he/she do it
To achieve this requires a customer focus where the contractor manages
customer problems with their assets. These clients have biases and
maintenance contractors well appreciate that they are there to keep clients
happy. With respect to this, clients are increasingly under close scrutiny with
regard to their budgets.
It is the client’s perception of operational liability that is important. This will
determine the whether or not they will accept recommendations for repairs. If
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 11 of 16
the risk is life threatening, then normally they will accept recommendations.
Risk assessment assumes a very close relationship with the client in order to
be accurate and meaningful.
Characteristics of a successful interface include:
1. Integrity - trust, relationship, ability to get on.
2. How do we communicate - open book.
3. What are we doing for the customer to understand (our value)?
Maintenance improvement is only possible through the collaboration between
the maintenance providers and the clients who rely on the availability of the
facility for their business to operate. Moving to a single monthly review of
accounts can be a sure way to create friction between contractor and client.
Sources of friction would be:
• Inaccurate recollection of work requests from three weeks ago.
• Presentation of a single large bill without warning as to the
accumulation of tasks.
• Expectation of a confrontational meeting with the incentive of one
side to simply reduce expenditure and on the other, to secure fee for
service.
• A lack of fitting the evaluation and the joint discussion of costs
breakdown into the business of operating a facility: maintenance is
seen as an overhead rather than the necessary part of the business
that it should be.
In addition to these considerations, there is an opportunity presented by the
daily meetings between the client and contractor to include a means for
repetitive, constant format reporting on the accumulation of maintenance
costs. For example, the Friday meeting may be associated with the hand
over of a one page summary of man hour accumulations of maintenance time
broken out across the main equipment areas. There are a number of benefits
to this proceeding:
1. Facility managers are required to assimilate the details of the
maintenance effort on a regular basis. In a sense the contractor
reports to them as critical staff providing an essential production
service, similar to the key internal staff, who report that everything is
running smoothly.
2. The facility managers are assisted to understand the effort
associated with the maintenance through simplified reporting which
provides an immediate overview of their costs on a weekly basis.
3. When the monthly bill is presented there are no surprises and any
issues that occurred during any of the weeks should have been
resolved when the weekly report for that period was issued.
4. Facility managers can more confidently sign off maintenance
expenditure, as they are more aware of how it accumulated.
5. Weekly data is now available which allows a more immediate
reaction to problems such as over servicing a particular area in the
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 12 of 16
plant. The factory managers plus their support staff need to have
maintenance problems associated with equipment type or mode of
operation presented to them as swiftly as possible.
Monday review of
weekend problems and
forecast of week's work
Tuesday review of daily
log
Wednesday review of
daily log
Thursday review of daily
log
Friday review of
operating problems,
breakdowns and
maintenance requests
Review of weekly
overview of effort
expended on a machine
by machine basis
- Check 1 week's work history
- Breakdown distribution
- Inventory review
- Procurement review
Interface between Facility
Manager and Service
Provider
Monthly review of
contract account
- Breakdown of costs
- Review of unnecessary work
- Procurement review
- History of poor performing
equipment
- Spare parts policy issues
- Technical difficulties requiring
engineering support
Monthly review with
Client Manager
- Accountability of costs
- Unnecessary work review
- Procurement reports
- Technical problems requiring engineering
support
- Outstanding issues
Figure 6.1 Review of interface between client and contractor
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 13 of 16
Hence the review process may follow the procedure outlined in Figure 6.1.
The current meetings are extended to cover the issues nominated. It is
important to realise that this is not a new system: it is an extension of the
method for liaison that is already in place. It also recognises the following:
1. Maintenance management, irrespective of who carries it out, requires
engineering support to counter design-based issues and client complaints
to answer operating-based problems.
2. There needs to be specific accountability of the people, irrespective of their
organisation, who are responsible for spending maintenance money. The
costs in this system are divided between request for labour and
procurement.
3. The presentation of reports are a build-up of simpler reports so that no one
receives any surprises. Further the reporting is sufficiently frequent to
ensure an immediate response to any problems. The reporting is
undertaken to ensure efficient assimilation of the knowledge. To achieve
this the reporting is simple and normally as concise as possible.
4. There is an expectation that managers responsible for operating decisions
will be sufficiently well informed regarding the forward capability of their
equipment that their specified targets will not be jeopardised through loss
of performance or lack of reliability.
7. Opportunities for Value Adding in the Contract
A package for a proposal for value adding is set out by way of a timetable of
work. The project would likely target one significant building or part of a
building. A preferred choice would be one with a multiplicity of systems.
1. Check asset list of target building
2. Group assets into generic systems, eg air conditioning, lifts, hydraulics,
structure and fabric, glazing, misc. light and power, electricity
distribution and so on.
3. Review work history and reliability in each of these area. This to
include:
• Past maintenance records
• Past problem areas
• Inspection strategies
• Drawings
• Energy measures
• Fault reporting systems
• Design performance specification for major assets
• Definition of non-performance for major assets
4. Report on asset base and its management
5. Review and assess the application of an improvement methodology for
the planning of asset management.
6. Cross check past project’s methodology with application of method to
target building.
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 14 of 16
7. Develop and refine inspection check sheets for manual audit process,
necessary to supplement continuous monitoring.
8. Review opportunities for continuous monitoring with existing
instrumentation. How is the data to be managed and analysed, plus
used to provide early warning of applied stressors to the relevant
module?
9. Collect preliminary data and test aspects of data management and
reporting.
10. Map the information system that pertains to the building asset
management, allocate potential responsibilities for collection, analysis
and review.
11. Report on feasibility of improvement including discussion of peoplebased
threats to technical effectiveness.
The improvement methodology for value adding is streamlined into four
principles:
• Measure process – either automatic or through manual audit
• Identify process inefficiency or non-compliance with design performance
targets
• Diagnose root cause for inefficiency or non-compliance
• Correct root cause
The commencement phase for a value add project includes the following:
• Inspection tour of the target building
• Access to building records as designated above
• Introduction to maintenance staff as well as operational (i.e.
inhabitants) staff
• Time once per week for a brief meeting to check progress
• Provision of access to buildings as required by the contractor
Conclusion
Much of what has been described in this paper is related to simple quality
principles. Quality is seen as an overhead but it needs to be introduced in a
way that improves the business. This can include:
• Collation of information and reporting - collecting the RIGHT data
• Analysis of control information
• Correspondence to the client, setting out advantages and
disadvantages of recommendations
• More understanding and expectations of recommendations
It is important that the work is consistent and using quality control, a
contractor should be assured that the level of control is satisfactory and cost
justified. Work plans and strategies sometimes need to be reviewed at a
corporate level to find deficiencies in the system.
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 15 of 16
Improvement required in contractor work includes:
• Attention to detail
• All actions covered
• Generation of reporting to customer
• Reporting financials
• Protection control: do the estimated costs meet actuals
It is clear that a contracting company has to distinguish themselves in the
market place by assisting clients to raise themselves to new levels of
achievement, specifically maintenance excellence. No company in the
market place has field staff across the board consistently applying all of the
principles contained in this paper. This is due to key personnel not buying
into the otherwise good practice techniques, not being aware of what
represents good practice or working under a system that does not lend itself
to the easy application of the principles.
Inherited weaknesses that are either being addressed or still need to be
overcome include:
• Inadequate equipment
• Inadequate trades skills
• Lack of familiarity with equipment
• Incorrect allocation of costs
• Inefficient and often inherited work practices
• Poor communication with the client
• Cumbersome financial system (including billing)
• Employees taking work place risks
• Inaccurate recording of technical details in the field
• Poor leveraging of technical support across the company
However, a maintenance contractor has the right to have expectations of their
client if maintenance management is to be optimised. Problems facing the
contractor will include:
• Ambiguous contract document
• Demanding additional (and unpaid) services
• Management of the contract in accordance to the superintendent’s
preference and not as written
• Insufficient time for familiarising the new contractor
• Poor plant records
• Incorrect or limited specification of the plant to be maintained
• Poor lines of communication
• Cultural antagonism to contractors
The benefits of outsourcing maintenance in terms of cost reductions,
improved deployment of staff, and the introduction of new technical skills is
undeniable. However the drive to distinguish themselves in the market place
IIR Building Maintenance and Management 2000
R. Platfoot - Covaris Pty Ltd Page 16 of 16
plus the needs of the maintenance discipline are taking both contractors and
clients into new places of cooperation and technical application that would not
have been considered even a few short years ago.
Acknowledgements
The author wishes to thank various firms for their input over the years into the
contract management research by the author. Specifically he would like to
thank Asset Services, Skilled Engineering and Kilpatrick Green FM.