|
Informed Maintenance
Planning
R.A. Platfoot
University of New South Wales
Sydney NSW 2052
The starting point for improving maintenance planning is the establishment
of a maintenance policy which embraces a work flow system, various techniques
in monitoring reliability and work practices, and anticipates plant problems
rather than reacts to them. This means that the company has a commitment
to sustaining an information base which requires accurate data collection,
effective management and timely disbursement of reports. The planning
has to be reasonable, considering the level of available resources and
the speed with which they may be dispatched.
1. Introduction
There are two primary tasks associated with maintenance management: planning
the optimum schedule of work and ensuring that the effort has been effective.
It would be reasonable to suggest that the more intensive effort is associated
with the first area of work: it has to be responsive to both business
objectives of the plant and the current integrity of the equipment. Planning
has to incorporate a variety of task types from breakdown work, preventative
maintenance and survey work, [1]. In addition, it has two modes: planning
for overhauls and day to day tasks required for operating plant. Hence
planning absorbs a large portion of time for personnel ranging down from
the maintenance manager, the planning group and the trades staff who are
responsible for executing tasks.
Maintenance is necessary as a function of design issues, the onset of
damage mechanisms, sensitivity to operations and generally determining
the risk for a desired service life to be cut short. These issues are
relevant to improving the planning process so that problems are anticipated.
This provides a proactive approach rather than a reactive approach. Proactive
planning will ensure timely warning on the need to provide capital for
plant improvements and the possibility that a facility will not deliver
the required performance at some time in the future. It is this sense
of anticipation which represents the step forward of modern maintenance
planning over the primarily responsive approach adopted in the past.
2. Maintenance Improvement Model
A program for the improvement of maintenance within a company is set out
in Figure 1. The objective of this program is to provide a means by which
the assets of the company are operated and maintained with the knowledge
of their current and expected future capability, [2]. There are three
lobes to the process: condition-based maintenance, strategic planning
for the assets and optimisation of maintenance to suit production.
1
Plant Dictionary/ AssetRegisterDowntime RecordingCondition Assessment-
visual inspections- advanced inspectionsCondition-basedMaintenanceCyclic
PM SchedulesProduction Scheduling/Planned Utilisation ofAssetsReview of
productionStrategic Assessment- Stewardship- Investment- Labour strategyOutsourcing-
Selective- Informed controlPerformance-basedContracts- Cost reductionsKPI'sLiabilitiesTPM
Analysis- 6 Causes of failure- Cultural needs (eg teams)Control of the
integrityof the assetsFMECA/ Risk Analysis/Priority settingLife Prediction-
3 stages life analysis- Cycling studiesCriticality of major assetsStrategic
requirementsof maintenanceStrategic policy on a facilityby facility basisRCM
analysis- priority setting- tactical policy30 year planTime to retirementOpportunity
basedon other businesssystemsFocus neededCurrent focus
Figure 1 Maintenance Improvement Strategy
Ideally one would like to do everything at once, but no company can sustain
more than about four or five improvement tasks at any one time. As a consequence,
a company needs to move to elements of condition-based maintenance first,
then to adopt improvements in each of the other two lobes, and then to
take stock of their future
2
management of their assets. There is no clear advantage in whether to
progress the strategic lobe or the production optimisation lobe before
the other.
The condition-based maintenance lobe has two paths incorporated in it.
The left hand path following downtime tracking and inspection strategies
are primarily focused on operations staff better understanding the capability
of the equipment which they control. The right hand path is for the maintenance
staff to analyse their performance and to improve their planning. Reliability-centred
maintenance is a powerful, risk-based technique [3] which we employ in
the right hand path to reduce the total amount of maintenance undertaken.
But we also recognise that it is only possible to achieve this by improving
the surveillance of the plant so that problems which would normally be
prevented by a greater preventative maintenance program, are anticipated
and corrected before downtime arises.
The strategy behind Figure 1 is that it shows the dependency of activities.
For example, condition-based maintenance cannot be imposed on a site which
practices reactive maintenance without first setting up a comprehensive,
cyclic preventative maintenance program. In addition, maintenance performance
improvement is only possible when a mechanism which is the equivalent
of a work order allows effective information capture. An inspection system
should not be rolled out prior to the establishment of a downtime tracking
system, without running the risk of creating unnecessary inspections and
missing others which would prevent failures such as have arisen in the
past.
3. Strategic Goals versus Day to Day Management
There are two levels on which maintenance planning is undertaken: the
strategic level and the day to day organizing of maintenance tasks. The
strategic planning of maintenance is concerned with whether or not the
equipment which makes up the facility will meet both its current requirements
and those set for the long term. Hence strategic planning requires an
appreciation of the business requirements and the manner in which operations
will degrade the plant, [4]. For example, if it is forecast that the facility
will produce smaller batch sizes and that a greater degree of flexibility
will be demanded in the future, then strategic planning has to accommodate
possible increases in the maintenance budget due to accelerated wear out
from change overs and stoppages. Alternatively, if it is determined that
the facility is becoming less efficient than corresponding plants elsewhere
in the company, then strategically it would be intelligent to reduce the
maintenance expenditure and tolerate a possible deterioration in the equipment.
This may be partially offset as the throughput reduces as more efficient
plant elsewhere picks up more of the production burden.
The vision for one maintenance group in a medium-sized manufacturing company
is:
To provide a cost effective and efficient maintenance service by changing
the focus from the existing reactive service and evolving into a proactive,
predictive, preventative maintenance service.
3
This vision will suffice while this group progresses from a cyclic maintenance
program into a condition-based maintenance approach to planning. As the
group grows in its capability and in its confidence of what is can achieve,
then the vision will expand. The end vision for a maintenance provider
may read something like:
To ensure that the assets of the company will be reliable. This will be
achieved by anticipating deterioration and addressing its root cause by
technical means and education of company personnel. The timing at which
these actions will be initiated will be set through a mature financial
appreciation which takes into account the optimum time at which items
may be removed from service.
This vision statement sets out the primary purpose, how it will be achieved
and when. The relevant who for this statement is the maintenance group
for whom this is the vision. The relevant what (has to be done) is left
for more detailed strategic documents.
The day-to-day objectives of maintenance requires work to be grouped into
two categories: maintenance and plant improvement, [5]. The distinction
needs to be made in order to differentiate the costs of retaining equipment
in its working condition as compared to improving the process. The types
of work which need to be tracked on a daily basis includes:
Unplanned work: Any work arising that has not been included in a schedule
of work. This includes breakdowns, requests for operator assistance and
opportunistic work undertaken while the trades person in the vicinity.
In some cases this work does not attract a production stoppage penalty,
but all categories represent periods when the timing of the work is not
controlled.
Planned work: This will include preventative maintenance tasks (which
prevent a breakdown), predictive maintenance inspection (to determine
condition of equipment) and scheduled overhaul work, all of which form
a schedule of work. Labour and parts are prepared in advance in order
to complete these tasks.
Capital Improvement: Work which requires managerial or corporate approval
of funds. This work may fall outside of the maintenance contract and therefore
a tendering process may be in place to win the work. There may also be
a requirement to carry out justifications and design work as part of the
preparation to tender.
Plant improvement: Any works that require capital expenditure to the limit
of authorisation of the plant managers or equipment upgrades as part of
an ongoing improvement program. This work may take the form of a project
that has been developed by operations staff and would generally be completed
by the maintenance provider. These projects can sometimes be experimental
and it is therefore important to clarify the scope of work as recorded
on the work order.
Raising and acquitting a work order is a key to the success of the maintenance
process. Although the system can be fast tracked to complete urgent work
the loop must be closed
4
in order to capture all of the required information that will allow the
management team to make value judgements as to the integrity of the equipment.
Another key issue in the tracking of data via the work order system is
that of finances. It is not only important to invoice the correct value
to the owner but also to be in a position where the maintenance provider
can measure his performance and apply suitable improvement programs.
4. Work Flow Systems
The fundamental strategy is first of all influenced by whether or not
breakdowns may be tolerated. While all breakdowns are undesirable, there
is an added investment required to ensure that they absolutely never happen.
For the majority of industrial facilities this investment is not warranted
in terms of the business objectives. A grading of industrial facilities
would look like:
99.9% - high investment justified by financial return
90% - best practice service facility
80% - best practice manufacturing facility
60% - average performance facility which is not world class
40% - poorly performing facility
The rankings may be interpreted as follows: if a facility has a reliability
such that its maximum utilisation level is between 90 and 99.9%, then
it equates to a best practice service facility such as a sewage pumping
station or a power station. Note that we use the term utilisation level
and not more common terms such as availability or capacity factors. This
allows us to include setup times but not idle times when there is no demand
for the product or service. The reason for this is that there is no guarantee
that a low demand unit receives the maintenance investment necessary for
it to operate at higher levels of utilisation.
We note that the industry standard for costs of work is as follows:
Cost of Breakdown = 3 × Cost of PM = 9 × Cost of PDM
where PM is preventative maintenance and PDM is predictive maintenance.
This rough approximation is based on the fact that Breakdown work includes
cost of lost operation, premium time rates and possibly urgent purchase
of material. The PM work covers the cost of material (possibly up to 60%)
as well as labour plus the cost of access, whereas PDM is largely a labour
cost.
If we consider the strategy of maintenance, then we may form the table
below to collate the necessary information linked to a strategic outcome.
Following the gathering of this information we then need to consider the
following questions:
1. Do we have a well managed work flow system which captures the necessary
data to provide the information required in the above table? 5
2. Where are we spending our money and do we need to reallocate the resources?
3. Do we sufficiently audit our capital spending such that we are investing
in the future of the equipment and not overcoming the mistakes of the
past?
Past experience
Future prospect
Strategy
Downtime rate
Plant condition
Work order history
1. Improve utilisation
2. Recover integrity
3. Optimise planning
Production expectations
New technology
Life assessment
4. Target equipment
5. Capital planning
6. Capital planning
In the first instance we need to map a work flow system by which we can
measure and hence manage the process, [6]. It is the first step towards
firming up what data needs to be captured, at what stage it is trapped
and where it ends up. An example of a proactive maintenance work flow
system is laid out in Figure 2. There are three types of work identified
in this system, which follow the categories discussed in the previous
section:
1. Work over which there is no control of the timing
• Equipment failure
• Partial loss of availability which has to be regained
• Failure of return to service
• Secondary damage which needs to be immediately rectified
2. Planned work over which there is control of the timing
• Cyclic preventative maintenance procedures
• Cyclic inspection requirements which require the plant to be off
line
• Cyclic requests for condition monitoring with the plant on line
• Corrective actions which result from either secondary damage associated
with a failure or identification of a problem on the plant
• Completion of an outstanding piece of work which could not be
completed earlier due to resources, access, lack of spares, etc.
3. Plant improvement work which will lead to an integrity upgrade, a production
enhancement or the elimination of a potential risk. Typically this work
can wait until a suitable time such as an outage.
6
Breakdown Incident- forced outage- partial loss ofavailability- failure
to return toserviceBreakdown Work OrderCheck for otherproblems/damage?Immediate
or canwait?YesImmediateCyclic InspectionRequirementsPlant out ofserviceinspectionPlant
inserviceinspection orconditionmonitoringPlanned Work -Work Order PlanningSystemWaitWork
needs plantshutdown?Shut down work planShut downWork can becompleted?NoYesProblem
detectedwhen work isundertaken?YesStopNoDesign Analysis/Production ReviewCurrent
plantcondition needs tobe determined?YesPlant improvement workspecifiedNoCyclic
PM Work OrdersIdentification of newwork specificationsDowntime HistoryCyclic
PlanWork HistoryCondition HistoryProcedures
Figure 2 Maintenance Work Flow
No condition monitoring or plant inspection activity should be carried
out unless there is a specific work order, naming the timing of the activity,
is released. The maintenance system cannot contain the information resulting
from the activity but the incidence of the activity has to be logged in
the maintenance system.
We may distinguish between a number of information systems which have
different purposes:
7
System
Content
Purpose
Maintenance System
Cycle times for standard activity
Work procedures
Logging of work order activity
Manage and log the work effort invested into the plant.
Downtime (Partial Loss of Availability) System
Log incidences of loss of reliability/availability
Identify equipment-based threats to the business.
Plant Condition History
Record the results of inspections and condition monitoring activity
Relate the condition of the plant and identify areas of possible weakness,
A plant item may be considered to need attention if:
• The maintenance system identifies that we are spending too much
money on it.
• The downtime system identifies frequent failures there.
• The plant condition history identifies that its condition is degrading
at too rapid a rate.
It is not possible to combine or integrate these systems since their underlying
philosophy is quite different: they have a different purpose, the timing
in which data is collected is fundamentally different, different staff
classifications enter the data, and the data may well be analysed by different
groups with different objectives.
Measurements in a predictive maintenance context are collected to identify
the current condition of the equipment and to forecast the time for optimum
replacement. As such a single measurement has value in meeting the first
objective but little value for the second. Hence the maximum value of
data is realised when measurements can be analysed as a group collected
over time and in comparison across plant locations. This provides specific
obligations on the management of condition monitoring and plant inspection
data. The data must be held in a manner which allows the trending of the
data to provide an impression of what the future will hold. The data must
be objective in order to allow comparison; hence inspection results cannot
be solely comments but must have some form of quantification. No measurement
is made without first identifying the analysis which it will feed, the
outcome from that analysis and the decision support such analysis would
provide.
5. CMMS Feedback
8
Improvement processes combine both a field or plant activity and a back-up
information activity, typically conducted through the computerised maintenance
management system (CMMS). The second item is as important as the first
in order to ensure that improvements are documented, information flows
and decision making is informed, [7]. This ensures a cultural improvement
plus the success of improved communications. If people expect to have
certain information supplied to them, breakdowns in the communication
flow will generate attention on trouble spots which are indicative of
more fundamental problems such as neglect or waste through repetitive
work.
A comparison of downtime and maintenance performance data is shown in
Figure 3 for a heat treatment furnace. The data spans about 10 months
and does not include about 10 cyclic maintenance work cards, some of which
are carried out on a monthly basis.
Downtime analysis
Work order response performance
Figure 3 Analysis of SAS Dynavac furnace
There are some clear mismatches between the data: for example, 35 downtime
incidents were recorded but 50 breakdown work orders were logged. We expect
that the downtime data is reasonably correct but we may be missing some
very brief incidents, or equally likely we are seeing evidence of repeat
visits to the same failure. The data is providing us with a basis for
further investigation.
The balance of PM to breakdown work order is not satisfactory, but the
scheduling of PM’s is also poor with 15 PM’s being blamed
by operators as preventing the use of the asset. The downtime analysis
is owned by production staff and gives substance to their observations
in a meeting with maintenance staff. On the other hand, the work order
performance analysis put forward by maintenance shows how they are providing
resources and an analysis of the details of each work order will demonstrate
how they are currently addressing the downtime problems recorded by production.
If we consider a history record for two breakdowns which occurred on this
machine within one month of each other we gain further insight into the
maintenance performance.
9
Breakdown on 9/9/1996
Breakdown on 3/10/1996
Figure 4 Breakdown work order samples
The furnace operates in a gritty environment so fouling of the filters
is a reasonable expectation. If the two cards are compared, it took some
time for the maintenance providers to respond to the September 1996 failure
and the work was actually discharged
10
one day prior to the October failure. This job was attended to and acquitted
on the same day the problem was registered.
In both cases the risk to the plant was minor:
September breakdown - Risk A: No risk to plant operations
October breakdown - Risk B: Exposure to risk if another component fails
The second job required 5 hours to fix. It is not known whether or not
this includes travel time to the job which is an issue since the furnace
is located on a large jet base. In looking at the record of what was done,
in both instances the filters were cleaned on other fans. This may be
taken as an example of competent practice, but in fact suggests that the
preventative maintenance program is lacking: why aren’t the filters
of these fans cleaned before the fans fail? Why weren’t all of the
filters of all fans on this furnace cleaned when attending the September
breakdown? In other words, where is the planning role working to prevent
a breakdown call out, particularly when a heads up was provided that filters
were dirty during the September call out? This is not the fault of the
trades person, but rather the planning system associated with caring for
this unit.
At this particular site, the type of information provided above has been
given to the superintendents of the production process which uses the
furnace. As these middle managers are educated in the system, there is
an expectation that they will lead inquiries such as the questions raised
above. Similar to many modern CMMS’s, the information I snow available
to the company, but a system is required to exploit it.
The elements of such a system include:
1. Production own the downtime data and meticulously record failure events,
being particularly careful to log the reason for downtime.
2. Production attempt limited inspections, in keeping with their technical
expertise, but raising their awareness of the condition of the assets
that they use.
3. Production move to a greater sense of ownership of the assets, demanding
more detailed information from maintenance regarding the condition of
their equipment and the service provided by maintenance.
4. Maintenance review the history of their performance, particularly focusing
on breakdown attendance. Where could work have been anticipated?
5. The two groups jointly review the inspection program in the light of
information raised under items 2 and 4.
There are two key terms here: stewardship for production and client service
for maintenance. Both terms set obligations on each party.
6. Control of Personnel Dispatch
There are many sources of internal waste associated with maintenance.
These include:
11
1. Travel time to and from a job
2. Additional travel time to collect spare parts/tools necessary for a
job
3. Waiting for access to a machine/site
4. Wasted time due to lack of knowledge - design information, correct
procedure, appropriate diagnosis of a problem
Much of this waste can be eradicated through the employment of a planned
maintenance route which encompasses a list of the following:
• Path along which the trades person must travel
• Prepared list of spares and tools
• Provision of detailed instructions and access to support documentation
By implementing this approach, a maintenance provider will optimise the
use of their trades people. If the maintenance routes are not planned
then the trades person will rush from one job to the next with the outcome
that less time is available for diagnosis plus the guarantee that the
repair represents a permanent fix.
The key person in the maintenance chain is the equivalent to the planner
who is responsible for allocating tasks and planning the work. Hence this
position has to be formed on behalf of the operations client so that a
person can direct maintenance traffic throughout a facility.
Work can be allocated on the basis of three parameters:
1. Criticality of equipment
• Agreed levels established in the contract
• Subject to alteration due to changes in operations
2. Risk outcome - outcome if work is not done
• Human safety, environment, availability, minor hazard
• Statutory requirements
3. Potential to batch a job with other necessary work
• Function of the location of resources
• Minimise internal waste
A dispatch model needs to be established for an organisation which suits
the manning structure and the allocation of responsibilities between,
for example, different groups who provide a maintenance function.
7. Conclusion
The starting point for improving maintenance planning is the interface
between operations and maintenance, to identify sources of uncertainty
which would adversely
12
affect the planning and execution of maintenance tasks. In particular
the focus needs to be on the capability of the two groups to work together
to reduce the maintenance costs.
In one study conducted in a medium-sized manufacturing company, four primary
problems were identified:
1. Lack of accountability in raising requests for maintenance
2. The need to provide an overview of the maintenance system which is
in place
3. Demonstration of the optimisation of maintenance tasks and the sustaining
of this effort in the future
4. Inventory management and the need for identifying appropriate availability
of spare parts including the reduction of both on-site stock and the reliance
on overseas suppliers.
The answers to these problems are straight forward systems which have
had reasonable success in other manufacturing environments, both in Australia
and overseas, and which have been described in this paper.
The paper specifically addressed the management of maintenance work plus
the need for ensuring the accuracy of downtime tracking. This is not a
device to be used for the advantage of either operations or maintenance,
but the vital supply of technical information upon which a proactive maintenance
system may be based. The discrepancies between the records in the two
systems is the focus of a meaningful discussion which will improve maintenance
planning.
While data has to be collected to improve decision making, it has to be
delivered within effective reports which suit various levels of readership.
The presentations made in thsis paper were pleasing to the eye and relied
on both graphics and a blocked layout of comparable information. The ability
to scroll through such information and providing access by operations
managers to the details will improve leadership in maintenance improvement
by the people who will benefit the most: operations.
Acknowledgments
The author thanks the many companies who have participated in the maintenance
research and development program.
References
1. R.A. Platfoot, Reduction of plant downtime due to informed maintenance
planning and tailoring the maintenance system for production, Maintenance
Management Strategies, IIR Pty Ltd, Sydney, February, 1997.
2. R.A. Platfoot & G. Garner, Production-driven Optimisation of Maintenance
Resources, SAMA 97, Strategic Asset Maintenance in Australia, 1997, The
Institute of Engineers, 16-17 July 1997, Sydney.
13
3. J. Moubray, Reliability-centered maintenance, Butterworth Heinemann,
1991.
4. B.S. Blanchard, D. Verma & E.L. Peterson, Maintainability - a key
to effective serviceability and maintenance management, J Wiley &
Sons, 1995.
5. O. McKenzie & R.A. Platfoot, Quality manual for maintenance, ICOMS98,
Adelaide, 1998.
6. R.A. Platfoot, Maintenance Management, Master of Business and Technology
course, University of New South Wales, 1998.
7. A. Kelly, Maintenance and its Management, Conference Communication,
1989.
14
|